AG Processing's
Circulating Fluidized Bed Boiler
Project Schedule Time Allowed for Mechanical Piping Installation: 154 Days Starting October 1st, 2007
Overall Project Length: 24 Months & Started October 1st, 2006
Project Description
Scope of Work
Mechanical & Process Piping: This included fabrication & installation of the following systems, Steam, Condensate, Boiler Feed-Water, Boiler Blow-Down, Chemical Feed, Boiler Drains, Boiler Relief Vents, Natural Gas, Ammonia Vaporization & Injection, Boiler Ash & Limestone Pneumatic Conveyor System, Ash Bed Cooling System, Boiler Blow-Down Heat Recovery System, Economizer Steam Soot Blower System, Treated Water & Boiler Feed-Water Make-UP
Piping Hanger & Support Systems: This included fabrication & installation of the following support systems, Roller Hangers with saddles for all insulated systems, Clevis Hangers on all un-insulated systems, Calculated Load Bearing Spring Hangers on steam systems, Structural Steel Spanning Members, Floor Stands & Piping Bridges
Piping System & Support Painting: This included one prime & one finish coat, color coded per piping system on all un-insulated piping & grey primer on all supports
Testing: This was hydrostatically done on all wet systems to 450 PSI & pneumatically done to 1 ½ times operating pressure on all dry systems.