Mesa Middle School
Castle Rock, CO

Project Statistics:
Owner – Douglas County School District RE-1
General Contractor – W.O. Danielson Construction Company, Ltd.
Architect – Christiansen, Reece and Partners, PC AIA
Mechanical Engineer – Smith Seckman Reid, Inc.
Contract - $3,506,717.00
Completed – June 2008
Project Description:
Hard bid, plan and spec construction of 132,414 sq. ft. middle school.
Project Details:
The project consists of two stories of classrooms, a commons area, kitchen and gymnasium. Air handling units and mechanical room were located in a ‘drive-in’ crawlspace. Climate control was accomplished with twelve (12) air handling units, five (5) high efficiency 50 HP boilers, a 315 ton chiller, a 50,000 CFM cooling tower, VAV terminals, split systems, cabinet and unit heaters, a four pipe heating/chilled water loop.