Project Description:
MMI performed the mechanical portion on this plan / spec project which was a new addition / remodel of the hospital. The project included a complete upgrade of the mechanical system throughout the building. Phase 1 of the project started with the new north office addition. Phase 2 of the project was the new south ambulance garage addition. Phase 3 was the remodel of the existing facility.
Project Team and Statistics
- Architect: Jackson-Jackson & Associates
- Mechanical Engineer: Farris Engineering
- General Contractor: Hampton Construction
- Completion Date: January 2012
- Bid Type: Plan and spec
Major Program Spaces
- New construction – 12,300 square feet
- Existing renovation – 12,220 square feet
Project Responsibilities
- Hot water heat Piping
- Chilled Water Piping
- Domestic Water Piping
- Waste and Vent
- Compressed Air
- Medical Gas and Certification
- Sheetmetal / Air Distribution
- Temperature Controls
- Balancing
- Mechanical Equipment Setting
- Insulation