Education
We support educational facilities with safe, efficient, and cost-effective mechanical systems. Our work keeps classrooms comfortable and learning uninterrupted year-round.
The project consists of two stories of classrooms, a common area, kitchen and gymnasium. Air handling units and mechanical room were located in a crawlspace. Climate control was accomplished with seven (7) air handling units, a four pipe heating / chilled water loop, three (3) high efficiency 3,000 MBH boilers, a 200 ton chiller, a 32,500 CFM cooling tower, Ice Storage Tanks, VAV terminals, split systems, cabinet and unit heaters. Midlands Mechanical, Inc. performed all of the mechanical and plumbing work.
Project Team and Statistics
- Architect: Christiansen, Reece and Partners, PC AIA
- Mechanical Engineer: Envision Mechanical Engineers, Inc.
- General Contractor: JHL Constructors, Inc.
- Completion Date: July 2009
- Bid Type: Hard bid, Plan and spec
Major Program Spaces
- New construction
- 2 story middle school
- 32,414 square feet
Project Responsibilities
- Hot water heat Piping
- Chilled Water Piping
- Domestic Water Piping
- Waste and Vent
- Acid Waste and Vent
- Roof Drains
- Natural Gas
- Sheetmetal / Air Distribution
- Insulation
- Chemical Treatment
- Temperature Controls
MMI performed the mechanical portion on this plan / spec project which was a new facility.
Project Team and Statistics
- Architect: Jackson-Jackson & Associates
- Mechanical Engineer: Farris Engineering
- General Contractor: Hampton Construction
- Completion Date: January 2012
- Bid Type: Plan and spec
Major Program Spaces
- New construction – 12,300 square feet
- Existing renovation – 12,220 square feet
Project Responsibilities
- Hot water heat Piping
- Chilled Water Piping
- Domestic Water Piping
- Waste and Vent
- Compressed Air
- Medical Gas and Certification
- Sheetmetal / Air Distribution
- Temperature Controls
- Balancing
- Mechanical Equipment Setting
- Insulation
Mechanical and plumbing scope for a new 36,000 SF CTE Center and renovation of an existing 11,000 SF industrial shop building, including HVAC, hydronic, domestic water, sanitary, and storm piping systems.
Midlands Mechanical, Inc. served as the mechanical and plumbing contractor for the Jefferson High School CTE Center Addition & Renovation in Greeley, Colorado. This facility provides new educational spaces dedicated to welding, construction trades, cosmetology, culinary arts, early childhood education, and other hands-on learning programs. The mechanical scope covered all HVAC, plumbing, and associated control systems required to support these high-performance learning environments, integrating energy efficiency, occupant comfort, and robust utility service.
Mechanical & Plumbing Scope Highlights:
- Complete HVAC system installation including new air handling units (AHUs), variable air volume (VAV) terminal units, and rooftop exhaust systems
- Hydronic heating and chilled water piping distribution throughout facility
- Radiant floor heating for comfort in occupied spaces
- Ductwork fabrication and installation for labs, classrooms, offices, and specialty areas (welding, cosmetology, culinary)
- Installation of lab-specific exhaust systems including fume hood ventilation and dedicated make-up air systems
- Snow melt system with slab heating loops, manifolds, sensors, and controls
- Building automation system (BAS) integration using DDC controls
- Domestic water service distribution to classrooms, restrooms, kitchen, laundry, and cosmetology suites
- Plumbing for specialty program areas: shampoo sinks, commercial kitchen fixtures, laundry equipment, lab sinks, and bottle fillers
- Sanitary and storm piping with roof drains, cleanouts, and sump systems
- Wet-pipe fire sprinkler system design and installation compliant with NFPA 13
Midlands Mechanical, Inc. Responsibilities:
- Installation of complete mechanical and plumbing systems including piping, HVAC equipment, fixtures, and insulation
- Field coordination with structural, electrical, and architectural trades using 3D coordination models
- Procurement, delivery, and rigging of major HVAC equipment
- Startup and commissioning support for mechanical systems
- Assistance with O&M manual development, system training for district staff, and documentation per project closeout requirements
- Coordination and support for third-party testing, adjusting, and balancing (TAB) activities
Design + Construction Team:
Architect: Hord Coplan Macht
Mechanical Engineer: IMEG Corp.
General Contractor: Roche Constructors, Inc.
Mechanical & Plumbing Contractor: Midlands Mechanical, Inc.
Owner/Agency: Weld County School District 6
Little Raven Elementary School is the third new elementary school we have constructed for Littleton Public Schools over a 3-1/2 year span. This school is a 76,000 Square foot elementary located in Littleton Colorado. The school has 2 boilers, 6 Rooftop Units and over 85 hydronic VAV reheat coils. There are also over 120 plumbing fixtures in the school which also includes a commercial kitchen and dedicated 140 degree hot water system and water heater. There is a domestic water booster pump which feeds a 4” diameter domestic cold water main and 3” domestic hot water main running throughout the school as well as a 1-1/2” hot water recirculation line. Construction began in April of 2022 and completed in July of 2023.
The project consists of two stories of classrooms, a common area, kitchen and gymnasium. Air handling units and mechanical room were located in a ‘drive-in’ crawlspace. Climate control was accomplished with twelve (12) air handling units, five (5) high efficiency 50 HP boilers, a 315 ton chiller, a 50,000 CFM cooling tower, VAV terminals, split systems, cabinet and unit heaters, a four pipe heating / chilled water loop. Midlands Mechanical, Inc. performed all of the mechanical and plumbing work.
Project Team and Statistics
- Architect: Christiansen, Reece and Partners, PC AIA
- Mechanical Engineer: Smith Seckman Reid, Inc
- General Contractor: W.O. Danielson Construction Company, Ltd.
- Completion Date: June 2008
- Bid Type: Hard bid, Plan and spec
Major Program Spaces
- New construction
- 2 story middle school
- 132,414 square feet
Project Responsibilities
- Hot water heat Piping
- Chilled Water Piping
- Domestic Water Piping
- Waste and Vent
- Acid Waste and Vent
- Roof Drains
- Natural Gas
- Sheetmetal / Air Distribution
- Insulation
- Chemical Treatment
- Temperature Controls